W. O. Grubb makes sure U2's steel Claw grabs the limelight

24 November 2009

Assembling a U2 band tour stage.

Assembling a U2 band tour stage.

The band U2 has been rocking fans around the nation with its 360˚ world tour. In October four cranes from the fleet of W. O. Grubb were used to erect the elaborate stage at Scott Stadium on the University of Virginia campus in Charlottesville, VA.

The stage, designed in Belgium, features a 360˚ platform surrounded by a four-legged steel structure known as "the Claw." It stands 165 feet (50 m) tall and more than 300 feet (91 m) wide.

The stage - claimed to be the largest musical stage structure in the world - requires more than 120 truckloads to transport, and eclipses the previous record held by a Rolling Stones concert stage used a few years ago.

To erect the stage W. O. Grubb used two Liebherr LTM-1060/2s, a Grove TMS-900E and a Grove TMS-800E. The cranes lifted the steel structure into place and also constructed the surrounding light towers, sound booth, speakers and hardware.

Grubb spokesperson David S. Wheeler says the cranes chosen were selected because they could travel through the narrow tunnel leading into the stadium. After the concert crew and cranes were dispatched back to the stadium to disassemble "the Claw" and pack it up for transport in preparation for the next venue.

The U2 360° tour has provided a lot of work for crane and rigging companies around the world.

Belgian company Stageco constructed three identical stages for the tour. What makes the design distinct is the high-pressure hydraulics used to assemble and dismantle the 230-ton (207 metric ton) stage system.

Stageco developed the system based on Enerpac's Synchronous Lift System which allows the modular construction to rise to its 165-foot height quickly and safely.

But besides being functional, stages for these types of concerts much be spectacular, featuring glitz and special effects that audiences love.

Stageco has worked with U2 before, designing the stage for the band's PopMart Tour in 1997.

Over the years, the company has built stages for the Rolling Stones, Bon Jovi, Tina Turner, Elton John and Johnny Hallyday. Stageco provides technical design and manufacturing services, including logistics.

Since there is a short time between U2 performances, and seven to eight days are needed to assemble and dismantle the stage construction, three whole stages were constructed and are used following the "leap frogging" principle: one is used for the show, while the second is already being built at the next location and the third is being dismantled at the previous location.

One of the construction requirements was that the stage could be built and taken down again easily. The challenge for Stageco was how to assemble and dismantle the massive stage at each venue.

A solution also had to be found for the installation of the light and sound technics, and the special 60-ton (54 metric ton) video screen that has to be raised and lowered for each concert.

Chain hoists and winches are normally used for stages, with the support of light mobile cranes where required.

However, the load in this project was so great that a different solution was required. One of the alternatives considered was the use of extremely heavy mobile cranes with a lifting capacity of at least 400 to 500 tons (363 to 454 metric tons).

However, there was doubt as to whether such cranes would fit inside the stadiums where the concerts were to be held and whether they could be stabilized sufficiently.

Plus, using such heavy lift cranes would be expensive and time consuming.

Another alternative considered was the use of hydraulic strand jacks. But Stageco eventually joined up with Enerpac to design a custom solution that was "plug-and-play."

Enerpac's Synchronous Lift System using high-pressure hydraulics was the answer.

The steel stage construction consists of a central "block" which rests on four legs, each made up of six sections.

The central block is gradually lifted off the ground in 38 steps and a section is added to each of the four legs after every six or seven steps. A temporary truss (lifting portal) containing a supporting frame at the top has been fabricated for each leg.

Each hydraulic unit, consisting of a pumps unit, four lifting cylinders and four locking cylinders, moves along the guide rails.

Within each truss, a hydraulic pump unit, four high-pressure lifting cylinders, each with an applied pulling force of 20 tons (18 metric tons), and four 0.5 ton low-pressure locking cylinders, are all attached to a supporting frame, which moves along the guide rails.

The complete hoisting system for each stage consists of 16 lifting cylinders, 16 locking cylinders and four fully hydraulic units. The lifting cylinders are fitted with a pressure transducer, a built-in stroke sensor and two proximity switches.

The hydraulic pump unit includes individual pumps -- one for the lifting cylinders and one for the locking cylinders.

The pump units are controlled according to the master/slave principle from a central operating computer on the ground, which has a touch screen with images showing the position of the various hydraulic cylinders and their position within the lifting portals.

The force of each lifting cylinder and each lifting portal is also displayed, along with the total force. What is more, a local PLC has been installed on each platform so that the lifting platform can be operated locally if necessary.

When the frame is lifted, the top beams are first raised one step hydraulically, and then locked mechanically using locking pins and hydraulic locking cylinders.

The bottom locking pins are then cleared hydraulically and the cylinders raise the load to the same height.

In this way, the four hydraulic units lift themselves in the lifting portals with the load, as it were, at a net speed of around 32 feet per hour. Lift synchronism is vital.

The operating computer's display shows that the load in the four portals remains in perfect balance, and also shows which steps in the lifting process have been completed.

The operator gives the system a command for each step. After the claw has been assembled, the pump units are lifted out of the portals using a mobile crane.

The system works according to the same principle but in the opposite direction when the whole construction is lowered and dismantled.

Stageco made no concessions in terms of safety. Every step in the lifting process is controlled, and the next step can only be performed when all the required conditions have been fulfilled.

The system also gives information on the position the load is in and how the tension is distributed during lifting.

The Enerpac system measures the forces continuously and in real time.

Although the operational speed is significant, Stageco considers safety to be one of the greatest advantages of this technology.

Since the three stages are travelling around the world over the next two years, there was also strong emphasis is also on reliability and durability.