Engineered Rigging facilitates a tricky power plant upgrade

Installing a new coal ash conveyor required innovative engineering and precision planning.

When it came time to replace its coal ash conveyor, the Ottumwa Generating Station faced a perplexing logistical challenge. The new conveyor was 110-feet long and weighed a hefty 138 US tons. Plus, it needed to be lifted 10 feet so permanent legs could be installed to support the structure. Adding to the complexity was the low headroom and congested space inside of the power plant. These factors precluded the use of a crane and bulky cribbing stacks. Engineered Rigging created a modular lift system for the project that can be customized for similar jobs in the future. 

After assessing the project’s goals, the Engineered Rigging team created a three-part lifting strategy using 3-D modeling to avoid surprises when the equipment reached the plant. First, the engineers identified how to move the massive conveyor adjacent to the boiler. They designed a system featuring 16 omnidirectional load skates each with a 10-ton capacity, and 12 custom-fabricated, 23-foot-long support beams, each with a 19-ton capacity. This solution enabled the company to translate the conveyer about 20 feet and position it on grade.

Engineered Rigging’s custom lifting solution safely elevated the heavy conveyor in a tight space.

The second part of the plan involved the development of a lift fixture to set four hoppers onto the conveyor. The custom fabrication for this portion of the project was completed at Engineered Rigging’s facility in Russellville, AR.

For the final phase of the project, Engineered Rigging developed a powerful, space-efficient solution to elevate the entire assembly 10 feet so that the conveyor’s support legs could be installed. For this task, Engineered Rigging created a customized lift system comprised of 24 lifting columns.

Given the length and weight of the conveyor, safety was a top priority. Engineered Rigging designed the lift system so that a single operator could remotely control the 24 lifting columns. In addition, as the columns raised the conveyor, they mechanically locked into place which enabled the installation of the legs without a suspended load.

The modular lift system was rapidly assembled inside of the plant in just two days of double shifts. The system lifted the 138-ton conveyer into place and positioned it on grade with a total lift time of only 30 minutes. Tear-down was accomplished in a single day of double shifts.

“By having a breadth of talent, heavy lift technology and fabrication capabilities in-house, Engineered Rigging is able to deliver rapid turnaround times for custom heavy lift solutions,” said Engineered Rigging President Christopher Cox, P.E. “From concept to completion, we fulfilled the Ottumwa Generating Station Bottom Ash Conversion Project’s needs in just 16 weeks,”

For this multi-faceted project, Engineered Rigging provided engineering consultants, design, fabrication, heavy lifting equipment rentals and onsite technical support. The modular lift system’s gauge and column spacing can be customized to accommodate lifted items that are various lengths and widths, making it a practical solution for numerous applications.