Fagioli subcontracted for impressive oil and gas project

19 May 2017

127425 main cover

Fagioli recently completed marine transport and installation operations for one of the most impressive oil and gas projects ever undertaken in the offshore industry.

“The installation scope covered the delivery of all modules to the assembly yard in Canada and their assembly into one topsides unit on a customized pier,” said Edoardo Ascione, president, Fagioli USA.

Fagioli was also subcontracted to weigh the larger modules for the project, including the Utility Process Module, the Living Quarters Module and the Drilling Support Module.

The project activity started in the fourth quarter of 2012 with the engineering phase taking place through the end of 2013. This was successfully completed before the beginning of site operations which took place from early 2014 to October 2016.

The platform modules handled by Fagioli, including grillage and temporaries, were the Utility Process Module weighing 48,501.6 tons, the Drilling Support Module weighing 4,299 tons and the Drilling Equipment Set weighing 4,078.5 tons. Ancillaries included the Flare Boom weighing 374.7 tons, the Life Boat Stations weighing 231 and 253 tons and the Helideck weighing 126.7 tons. 

To the Canada job site the Fagioli team mobilized 240 SPMT axle lines; strand jacks with a capacity up to 606 tons; a tower lift system for the lifting activity; crawler cranes with up to 1,488-tons of capacity; an elevator system with a 7,736-ton capacity; 64 skid shoes with capacities up to 1,102 tons each for the skidding load out and load in activity; and climbing jacks. All of this equipment was used in a variety of creative ways to lift and install the various sections.

The 354-foot tall Flare Boom was mobilized by 32 axle lines of SPMT during the load out and in operations. The Living Quarters was built at the assembly site, where it was outfitted with Life Boat Stations and a Helideck. The Drilling Support Module arrived on a barge.  Fagioli used more than 200 lines SPMTs to perform the load in of the 4,299-ton module with a length of 177 feet. The Drilling Equipment Set arrived on a transport vessel. Fagioli used more than 200 lines SPMTs to perform the load in of the 4,078.5-ton Drilling Equipment Station that measured 229.6 feet tall.

“Following the delivery of all modules to the assembly yard in Canada, Fagioli was called to prepare and perform one of the biggest load out operations ever performed in the  history of the offshore industry, executed after years of planning and engineering calculation and simulation activity,” said Ascione. 

This included the skidding operation of a 48,501.6-ton offshore Utility Process Module by means of 64 skid shoes on a semi-submersible ship in Korea. 

Amazingly tight tolerances

Following delivery by another contractor of the Utility Process Module to the assembly yard, Fagioli executed the load in operation onto the assembly pier.

Fagioli used strand jacks and towers to raise the Drilling Support Module to the height of 19 feet for positioning of the module onto the elevator system which would raise the module to a height of 118 feet, ready for skidding onto the Utility Process Module.  The Drilling Support Module was skidded onto the Utility Process Module in one direction and then transversally skidded and jacked down using climbing jacks onto its final position within extremely tight tolerances.

The Drilling Equipment Set – a 229.5-foot-tall, 12,139-pound drilling rig tower – was moved on site by a transport vessel onsite and loaded in by SPMTs. This very heavy module was then lifted onto the transport stools for final positioning onto the skidding system. The Drilling Equipment Set was lifted by the strand jack and tower lift system up to the planned height for the skidding operation. The skid shoes system allowed the final completion of the skidding operation onto the Utility Process Module. Final installations were the Flare Boom and the East Life Boat Station.  Fagioli’s scope of work ended in October 2016.

“This project was one of the most challenging and complex operations ever performed by Fagioli,” Ascione said. “The project represented one of the largest fleets of equipment used so far for the assembly of an offshore platform.”

One hundred percent of Fagioli coverage was required for all operations, including double shifts for the main installation.  At the peak, Fagioli had 225 workers on site. The engineering department was involved in the project since 2012 for concept development and calculation studies, including simulations.

STAY CONNECTED

Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up