Lampson capitalizes on dam work

By D.Ann Shiffler12 September 2011

At The Dalles Dam on the Columbia River, Lampson International mobilized a Manitowoc 4100W, a Manito

At The Dalles Dam on the Columbia River, Lampson International mobilized a Manitowoc 4100W, a Manitowoc 3900, a Grove 760E rough terrain crane and its Transi-Lift LTL-1100.

More than 4,000 dams in the USA have been identified by the American Society of Civil Engineers as deficient. In 2009, the ASCE determined that 1,819 dams are in the "high hazard potential" category. Needed work at dams includes everything from gate replacement to total reconstruction.

The problem with dam projects is that they are expensive and require extremely heavy lifting. Little by little, authorities are bringing deficient dams up to par. Lampson International has found a strong market for its heavy lift cranes on dam projects throughout the United States.

"The demand for cranes at dam projects is steady," says Kate Lampson of Lampson International. "Our Transi-Lift cranes can do this work and are often the crane of choice for dam construction and repair."

In 2010, the US Army Corps of Engineers and their contractor, Dix Corporation, approached Lampson about renting one of its Transi-Lift LTL-1200 cranes to perform a gate replacement at Lower Monumental Dam in Washington State.

The scope of the project included off-loading three new gate sections from a barge and removing the old gate section from the dam. The final element of the project was to install three new gate sections.

With a narrow staging area, Lampson was faced with a challenging assembly of the superlift crane. To assist with the construction of the Trans-Lift, Lampson used several of their own conventional crawler cranes and a Manitowoc 4100 equipped with a Ringer attachment. One of the most important aspects of a job like this is assembling and load testing the Transi-Lift crane.

Once the LTL-1200 was fully assembled, it stood 340 feet tall, had 3,200 Kips of counterweight. The crane was called on to perform lifts up to 648,500 pounds.

Lampson supplied four of its crew on site at the Lower Monumental Dam throughout the six-month project, which was completed in early 2011.

Also in the fall of 2010, the US Army Corp of Engineers and Dix Corporation again hired Lampson International to replace the downstream navigation lock gates at The Dalles Dam on the Columbia River, also in Washington.

The scope of the project included removing two old gate sections and laying them down for demolition, offloading two new gate sections from a floating barge and finally, installing the new pre-fabricated gate sections.

In order to assure the proper equipment for the project, Lampson International mobilized a Manitowoc 4100W, a Manitowoc 3900, a Grove 760E rough terrain crane and its Transi-Lift LTL-1100. The Transi-Lift was also assembled on site and rigged with 200 feet of main boom and 2,400 kips of counterweight. After assembly, the Transi-Lift was load tested for the approximately 870,000 pound new gate sections slated for replacement.

During the preparation for the new gate installation, weight estimates grew from 725,000 to 949,000 pounds. While the new numbers were within the Transi-Lift's capacities, Lampson was required to reconfigure the crane. This was completed in one ten-hour shift. The crane was reconfigured to gain 200,000 pounds of capacity.

The project spanned six-and-a-half months. Like most dam projects, there was a very confined work space for the cranes to operate.

"There are many unique challenges to doing dam work," says Lampson. "Our proprietary Transi-Lift cranes, coupled with exemplary planning by the Dix Corporation team, allowed the river to open on schedule for commercial navigation."

MAGAZINE
NEWSLETTER
Delivered directly to your inbox, World Crane Week Newsletter features the pick of the breaking news stories, product launches, show reports and more from KHL's world-class editorial team.
Latest News
In Memoriam: Earl Johnson, Jr., 1931-2023
ACT sadly reports that founder of Southern Industrial Constructors, Earl Johnson, Jr., 92, passed away on March 15. 
How can companies utilize the latest construction tech?
In 2023, as builders adapt to economic, supply chain and labor challenges, they’re turning to ConTech (construction technology) to boost performance.
The evolution of equipment and manufacturers in the SC&RA
In honor of the the Association’s 75th anniversary, this month spotlights member companies including Link-Belt Cranes, Trail King, Tadano, Kobelco Cranes and Liebherr. 
CONNECT WITH THE TEAM
D.Ann Shiffler Editor, American Cranes & Transport Tel: +1 512 869 8838 E-mail: d.ann.shiffler@khl.com
Matt Burk VP Sales Tel: +1 312 496 3314 E-mail: matt.burk@khl.com
CONNECT WITH SOCIAL MEDIA