OSHA published a final rule that is now in effect and clarifies certification requirements for crane operators while maintaining the employer’s duty to ensure that crane operators can safely operate equipment.

crane

Photo Credit: HB Weekly 

Under the final rule, employers are required to train operators as needed to perform assigned crane activities, evaluate them, and document successful completion of the evaluations. Employers who have evaluated operators prior to December 9, 2018 will not have to conduct those evaluations again, but will have to document when they were completed.

The rule requires crane operators to be certified or licensed, and receive ongoing training as necessary to operate new equipment. Operators can be certified based on the crane’s type and capacity, or type only, ensuring that more accredited testing organizations are eligible to meet OSHA’s certification program requirements. The final rule revises a 2010 requirement that crane operator certification must specify the rated lifting capacity of cranes for which the operator is certified. Compliant certifications that were already issued by type and capacity are acceptable under the final rule.

1. Certification

  • An operator can meet OSHA’s certification requirements by obtaining certification from an accredited, third-party crane certification organization, as described in paragraph (d).
  • An employer can also comply with OSHA’s standard by developing an employer-audited program as described in paragraph (e) and use this program to certify its operators.
  • Finally, per paragraph (c), operators can meet OSHA’s certification requirements by obtaining a state or local crane operator license that meets OSHA’s requirements.

2. Qualification

2000px-US-OSHA-Logo

Qualification is defined simply as whether or not you can correctly and safely perform the job you are asked to perform. Qualification also asks the question: Can you perform the task at the level required? It’s important to note that certification doesn’t necessarily lead to qualification.

3. Evaluation

  • In addition to ensuring that an operator is properly certified, an employer must also evaluate the operator to ensure that the operator has the skills, knowledge and ability to recognize and avert risk to operate the equipment safely.
  • This evaluation must be done by a person who has the knowledge, training and experience necessary to assess operators.
  • Once an operator has passed an evaluation on one piece of equipment, the employer may allow that operator to operate different equipment without further evaluation if the employer can demonstrate that operating that equipment would not require substantially different skills, knowledge or ability to recognize and avert risk.
  • The evaluation must be documented and provide the operator’s name, the evaluator’s name and signature, the date of the evaluation, and the make, model and configuration of equipment used in the evaluation.
  • The employer must be able to make the documentation of the evaluation available on the worksite for as long as the operator is employed (electronic availability at the worksite will satisfy the requirement).
  • When the employer needs to provide re-training, such as when an operator is not competent in a necessary aspect of safe crane operation, the employer must also re-evaluate the operator with respect to the subject of the re-training.
MAGAZINE
NEWSLETTER
Delivered directly to your inbox, World Crane Week Newsletter features the pick of the breaking news stories, product launches, show reports and more from KHL's world-class editorial team.
Latest News
Bigfoot Construction team joins outrigger committees
Jeff Steiner has joined the SC&RA outrigger pad resource task force, and he and his nephew, Eric Steiner, are members of the P30 standards outrigger pad subcommittee. 
Talbert celebrates anniversary of detachable gooseneck
First introduced in 1962, the hydraulic detachable gooseneck technology revolutionized safety in the trailer industry.
Sarens performs critical installation at nuclear site
The Tennessee Valley Authority (TVA) initiated a major nuclear refueling and maintenance outage so that four replacement steam generators could be installed at the Watts Bar nuclear plant.
CONNECT WITH THE TEAM
D.Ann Shiffler Editor, American Cranes & Transport Tel: +1 512 869 8838 E-mail: d.ann.shiffler@khl.com
Matt Burk VP Sales Tel: +1 312 496 3314 E-mail: matt.burk@khl.com
CONNECT WITH SOCIAL MEDIA